Skip to content
Client:

Alderman’s Chevrolet

Location:

Rutland, VT

kW Installed:
17.955 kW DC
Our Work:

Ballasted roof-mounted array of 17.955kW atop a new building at the Alderman's Chevrolet dealership.  In 2022, completed installation of a 125kW ABB Level III Fast Charger in the parking lot.  This project involved coordination with the utility on upgrades to accommodate the power draw, placing of charger and conduit in the paved parking lot, and initialization/programming of the charger on the EVConnect network.   The site was visited by then-US Representative, now US Senator Peter Welch, who took the opportunity to talk about the future of Electric Vehicles.